Coil Tubing Well Decommissioning Campaign

Project Overview

An operator needed to reduce well rehabilitation liabilities.

JJM personnel performed an options analysis (global) to estimate the economic benefit of performing plug and abandonment works involving vertical conventional wells with alternate technologies.

The analysis identified considerable cost savings could be realised by performing decommissioning activities in a staged approach with the use of Coiled Tubing to complete the upper abandonment.

JJM personnel then delivered the campaign of work that included obtaining relevant regulatory approvals, running of procurement processes to contract services for the lower abandonment and upper abandonments, wellhead cut and cap activities and well site reinstatement and rehabilitation. Full campaign supervision and project management delivery along with post campaign statutory reporting.

Project Details

Scope of Work

  • Development of plug and abandonment engineering designs

  • Procurement, tender and contractor management

  • Site rehabilitation and reporting

Key Challenges

  • Legacy well configuration

  • Well integrity remediation (free pipe and SCVF)

  • Remediation technology trials

Outcomes

The campaign was completed with a ~$250K saving per well in decommissioning costs and an approximate reduction in total ongoing well rehabilitation liabilities of approximately $17.5M.